Structural Concrete: Pouring Footings

IMG_0490.jpeg

Next week is expected to be fairly active. As planned (and mentioned in our last posting), we will be pouring concrete for footings on Monday 3/29. A second pour is scheduled for Friday, 4/2. We ask that everyone respect the “No Parking" signs along Vereda de la Montura during concrete pumping days, for everyone’s safety.

Additional rebar will be delivered on Tuesday 3/30 and again on Thursday 4/1. We are still working on the logistics and physical accommodations for running a crane directly inside the site. Until that work is complete, we’ll be bringing back the crane on Tuesday with removal on Thursday.

Previous
Previous

Schedule Update

Next
Next

Material Delivery Update