Material Delivery Update

IMG_0474.jpeg

We wanted to provide additional information regarding the material being brought to the site next week.

Firstly, the delivery has been postponed to Tuesday and Thursday (in lieu of Monday and Wednesday).

Additionally, these materials will be brought in via a crane from Vereda de la Montura. While we have made great efforts to route most deliveries directly into the site, this first batch of steel needs to be loaded in from the street. As you might notice, there are “No Parking” signs along Vereda to accommodate a temporary lane closure to allow for this delivery (as well as the first concrete pour which is now scheduled for Monday 3/29). The crane will be installed right outside the project site on Vereda and will be operational on both Tuesday and Thursday, after which it will be removed.