This week’s first concrete pour went smoothly and successfully. We thank everyone for their cooperation. (The photo above shows the concrete as it is being pumped.)

As schedules constantly shift, however slightly, we wanted to provide a quick update:
The next concrete pour has been moved up from Friday (4/2) to Thursday (4/1). Deliveries have also changed:

We will be receiving additional rebar on Thursday and Friday.

As our plans materialize, we’ll post updates on next week’s schedule.