Structural Concrete: Lower Level Complete, Pouring First Deck

IMG_0934.jpeg

The lower parking garage level (P2) is now complete. Concrete for the walls, columns and floor surfaces has been placed and finished.

For the past two weeks, we’ve been working on the P1 level. After erecting the decking, we installed much of the rebar and necessary conduit.

We are scheduled to pour this deck in two sections: one on June 2nd, and the second on June 8th. On both dates, the concrete pump will operate from Vereda de la Montura. Once the deck has been poured, we will place rebar for the walls, with shotcrete following shortly thereafter.