Schedule Update

Just a quick update on the structural concrete work: The first half of the P1 deck was poured on June 2nd, as scheduled and noted in our last posting. The second segment of this deck was due to be poured on Wednesday June 8th but has been rescheduled for Saturday, June 12th. The concrete pump will be stationed on Vereda de la Montura. We anticipate starting concrete operations at 9:00 AM.


Once the deck is complete, we’ll begin pouring the columns and finishing out the perimeter walls.