Structural Concrete: Final Deck Pours

L1 pour.jpeg

We are nearing the end of the structural concrete phase of the project: Concrete for both subterranean levels has been placed and finished. Last month, we also completed the ground floor (including its structural walls) and are now on to the second floor. This will be the final concrete level for the building, as the remaining floors transition to steel. We will still have other concrete elements to complete (such as driveways and ramps), but these are far smaller operations.

The podium will be poured on August 10th and 17th, with the pump on Vereda de la Montura. Once again, we are spreading the work over two separate days.