Excavation: Part Two
These past several weeks, we have been exporting dirt from the property to create the cavity for the underground garage. A significant portion of the dirt has been removed and the accompanying shoring is now installed. We will remove additional dirt early next week, and then pause the hauling operation for about 10 days to continue with the shoring installation. Once the entire shoring system is in place, we will resume and complete the export process, preparing the site for foundation piles.