Foundation Piles

IMG_0186.jpg

The foundation piles are now complete. The next major phase of the project will be the concrete parking structure. We will start digging footings and pile caps and then begin the slab-on-grade portion of the foundation. This work will commence in January, so the site will remain quiet throughout the holidays. You may see our crews demobilizing some of the equipment currently on the property, though the vast majority has already been removed.

Wishing everyone a safe, healthy and happy holiday season…

Previous
Previous

Site Prep for Concrete

Next
Next

Excavation: Part Three